The High Court has ruled that HS2 did not incorrectly procure the £1.3bn Old Oak Common station contract. Losing bidder Bechtel had challenged the megaproject’s award of the contract to a Balfour Beatty / Vinci / Systra (BBVS) joint venture on the basis that its…
The post HS2: judge dismisses Bechtel’s £1.3bn Old Oak challenge appeared first on Construction News.